5.4

Fixing the UPS

Please follow the steps below:
1
Before fixing the UPS in a designated installation area, please double check whether
the area's floor weight loading is sufficient to bear the UPS, external battery cabinet,
Delta or non-Delta external maintenance bypass cabinet and handling equipment (i.e.
forklift) to avoid accidents. For UPS floor weight loading information, please refer to
Table 5-1.
2
After the UPS is moved to the designated installation area, use a #17 wrench to stabilize
the UPS four leveling feet on the floor. Please note that the UPS must stand on the floor
stably and levelly without any tipping.
3
Use a 17mm socket wrench and three M10 screws
balance support on the pallet) to install the front balance support (removed during
the unpacking process) at the front of the UPS. Use the three expansion screws
(provided by qualified service personnel) to fix the front balance support on the ground
to avoid UPS movement. Please see Figure 5-3.
4
Use a 17mm socket wrench and three M10 screws
balance support on the pallet) to install the rear balance support (removed during the
unpacking process) at the rear of the UPS. Use the three expansion screws
by qualified service personnel) to fix the rear balance support on the ground to avoid
UPS movement. Please see Figure 5-4.
Modulon DPH Series
1
M10 Screw
X 3
(Figure 5-3: Install the Balance Support at the Front of UPS)
(Front View)
Expansion Screw
& Nut X 3
5-6
(originally used to fix the front
1
2
Balance
Support
Ground
(originally used to fix the rear
1
2
(provided
2

Advertisement

Table of Contents
loading

Table of Contents