You can install one AT-GS920/8PS witch in a row of the equipment rack or
two AT-GS920/8PS switches in one row of the equipment rack as shown
in Figure 31.
Figure 31. Rack Installation Options for the AT-GS920/8PS Switch
To install two switches in one row of the equipment rack, you need the
following items:
AT-RKMT-J15 rack mount kit
Cross-head screwdriver
To install two switches in one row of the equipment rack, perform the
following procedures.
1. Review "Selecting a Site for the Switch" on page 36 to verify the
suitability of the site for the switch.
2. Mount the AT-RKMT_J15 tray in a 19 -inch equipment rack using four
equipment rack screws. See.Figure 32 on page 64.