Figure 222: Installing A Three-Phase Wye Ac Power Supply - Juniper T640 Hardware Manual

Core router
Hide thumbs Also See for T640:
Table of Contents

Advertisement

Related
Documentation
Copyright © 2017, Juniper Networks, Inc.
Connect the AC power cord to the AC power source.
20.
Switch on the customer site circuit breakers to provide voltage to the AC power source
21.
cables.
Remove the ESD grounding strap from the approved site ESD grounding point. See
22.
the instructions for your site. Reconnect the strap to one of the ESD points on the
chassis.
Verify that the
AC OK
LED on the power supply faceplate is lit steadily, indicating that
23.
the AC terminal block is receiving power.
Switch the power switch on the power supply to the
24.
Verify that the
DC OK
LED on the power supply faceplate is lit steadily, indicating that
25.
the power supply is correctly installed and is functioning properly. The
blinks momentarily, then lights steadily.
NOTE:
After a power supply is powered on, it can take up to 60 seconds
for status indicators—such as the LEDs on the power supply, the command
output displays, and messages on the LED display on the craft interface—to
indicate that the power supply is functioning normally. Ignore error
indicators that appear during the first 60 seconds.

Figure 222: Installing a Three-Phase Wye AC Power Supply

T640 Three-Phase Delta and Wye AC Power Supply Description on page 106
T640 Three-Phase Delta and Wye AC Power Supply LEDs on page 109
Chapter 29: Replacing Power System Components
ON
position (
|
).
LED
DC OK
415