14.2 3 month maintenance actions

MAINTENANCE TYPE B (perform every three months)
The 3 month maintenance actions, listed below, may be performed by a trained projectionist who is familiar
with potential hazards associated with the product.
No.
Maintenance action
1
Clean the back air outlet vents of the lamp modules and Lamp Power Supply
(LPS).
2
Clean the housing of your projector.
3
Verify the internal clock of the ICMP with real time clock. Correct if needed.
4
Check the lamp module compartment and lamp fan for dust.
R5906693 DP2K-E SERIES 19/06/2015
14. Preventative maintenance actions
Remarks
Dust the vents using a vacuum cleaner
with brush attachment.
Remove excess dust on and around
the projector covers. See cleaning
instructions in this manual.
ICMP version 1.2.1 is required.
Communicator version 5.0 is required.
See user guide of Communicator for
detailed instructions.
Clean if necessary. Use a vacuum
cleaner with brush attachment to
remove dust.