installation procedure. Improper grounding can cause electrostatic discharge.
2. Back up all server data.
3. Power down the server .
4. Remove all power:
a. Disconnect each power cord from the power source.
b. Disconnect each power cord from the server.
5. Do one of the following:
a. Extend the server from the rack .
b. Remove the server from the rack .
6. Remove the access panel .
7. Install the secondary riser cage.
8. Install the access panel .
9. Install the server into the rack .
10. Connect each power cord to the server.
11. Connect each power cord to the power source.
12. Power up the server.
Installing a secondary full-height riser option
Installing a secondary full-height riser option
Prerequisites
Prerequisites
This option requires a dual processor configuration.
Before installing this option, be sure you have the following:
The components included with the hardware option kit
Any expansion boards or controllers you plan to install