a. Disconnect each power cord from the power source.
b. Disconnect each power cord from the server.
3. Do one of the following:
•
Extend the server from the rack.
•
Remove the server from the rack .
4. Remove the access panel.
5. Remove the air baffle.
6. Install the intrusion detection switch.
Installing a rear serial port interface
If a tertiary riser cage is installed, you can install the serial port into the slot 6.
Prerequisites
Before you perform this procedure, make sure that you have the following items available:
The components included with the hardware option kit
Procedure
1.
Power down the server .
2.
Do one of the following:
•
Disconnect each power cord from the power source.
•
Disconnect each power cord from the server.
3.
Do one of the following:
Hardware options installation
131