7.
Install the three-bay LFF rear drive cage option.
8.
Install drives or drive blanks.
9.
Connect the power and data cables.
10. Install the access panel.
11. Slide the server into the rack.
12. Connect each power cord to the server.
13. Connect each power cord to the power source.
14. Power up the server.
The installation is complete.
Riser and riser cage options
Hardware options installation
111