4.11.6 Installing Parallel Cables

Prerequisites
● The length and specifications of power cables on each UPS should be the same
● Ensure that the phase sequences of the mains input, bypass input, and output
● Connect power cables according to port silk screens.
Procedure
Step 1 Ground each UPS in a parallel system separately, and connect power cables and
battery cables.
Step 2 Choose a parallel mode and connect power cables to the parallel system based on
site requirements.
The typical scenario of a 1+1 parallel system is used as an example.
Figure 4-427 Conceptual diagram of a 1+1 parallel system
A dual-bus parallel system consisting of two parallel subsystems is used as an
example.
Issue 07 (2022-11-29)
NO TICE
to achieve current equalization in bypass mode. The power cables include
bypass input power cables and UPS output power cables.
power cables of each UPS are the same.
Copyright © Huawei Digital Power Technologies Co., Ltd.
4 Installation and Cable Connection
346

Advertisement

Table of Contents
loading

Table of Contents