Huawei UPS5000-H-1200K-NT User Manual page 288

Hide thumbs Also See for UPS5000-H-1200K-NT:
Table of Contents

Advertisement

UPS5000-H-(1200 kVA-1600 kVA)
User Manual (100 kVA Power Module)
Figure 4-303 Installing power cables between the UPS and the SmartLi
(1) Connect the ground cable of the battery string or its BBB box to the battery PE of the UPS
or the ground bar in the equipment room based on the site survey.
Step 6 Install top supports and covers of the battery terminal protective covers.
Figure 4-304 Installing top supports and covers
Step 7 Install input and output busbars.
Table 4-15 Power cable terminal requirements
Port
Mains input/bypass
input/output/PE
Step 8 Install power distribution units. (If the mains input and bypass input share a
power source, a power distribution unit must be deployed for the copper bars that
are not installed in the busway. Copper bars must not be exposed.)
Issue 07 (2022-11-29)
Copyright © Huawei Digital Power Technologies Co., Ltd.
Connecti
Bolt
on
Specificati
Method
ons
Crimped
M12
DT
terminal
4 Installation and Cable Connection
Bolt Length
45 mm
Torque
47 N·m
279