UPS5000-H-(1200 kVA-1600 kVA)
User Manual (100 kVA Power Module)
(4) Bypass cabinet
Step 2 Install expansion sleeves for expansion bolts.
1.
2.
3.
4.
Knock the expansion bolt into the hole until the expansion tube completely fits
into the hole. The expansion sleeve must be completely buried under the ground
to facilitate subsequent installation.
Figure 4-163 Installing an expansion sleeve
(1) M12x60 bolt
(4) Expansion sleeve
Step 3 Remove the side panels from power cabinet 1 and the bypass cabinet.
Step 4 Install the removed side panels on the sides of the left and right cabinets
according to the cabinet layout sequence.
Step 5 Remove the screws preinstalled on the copper bars in power cabinet 2 and store
them for future use.
Issue 07 (2022-11-29)
Drill a hole into the concrete floor using a hammer drill.
Partially tighten the expansion bolt and vertically insert it into the hole. Knock
the expansion bolt using a rubber mallet until the expansion sleeve is fully
inserted into the hole.
Tighten the expansion bolt.
Remove the bolt, spring washer, and flat washer.
NO TICE
Copyright © Huawei Digital Power Technologies Co., Ltd.
(5) Inductor cabinet
(2) Spring washer
(5) Expansion nut
4 Installation and Cable Connection
(3) Flat washer
(6) Concrete floor