4.9.3.1 Top AC Busway
Context
Figure 4-260 Copper bar positions
(1) Battery input
(4) UPS output
Procedure
Step 1 Install equipotential ground cable for cabinets.
Figure 4-261 Installing equipotential ground cable for cabinets
Step 2 Install power cables between the UPS and the inductor cabinet.
Issue 07 (2022-11-29)
Copyright © Huawei Digital Power Technologies Co., Ltd.
(2) Mains input
(5) Bypass input
4 Installation and Cable Connection
(3) Battery PE