UPS5000-H-600 kVA-FTN
User Manual (Singapore, 100 kVA Power Modules)
----End
4.10.5 Installing Parallel Cables
Prerequisites
● The length and specifications of power cables on each UPS should be the same
● Ensure that the phase sequences of the mains input, bypass input, and output
● Connect power cables according to port silk screens.
Procedure
Step 1 Ground each UPS in a parallel system separately, and connect power cables and
battery cables.
Step 2 Choose a parallel mode and connect power cables to the parallel system based on
site requirements.
The typical scenario of a 1+1 parallel system is used as an example.
Issue 02 (2023-11-07)
Figure 4-64 Cable connections between the backfeed protection card and
shunt releases
(1) Shunt releases (provided by the
customer)
NO TICE
to achieve current equalization in bypass mode. The power cables include
bypass input power cables and UPS output power cables.
power cables of each UPS are the same.
Copyright © Huawei Digital Power Technologies Co., Ltd.
4 Installation and Cable Connection
(2) 6 A fuses (provided by the customer)
111