Huawei UPS5000-H-1200K-NT User Manual page 291

Hide thumbs Also See for UPS5000-H-1200K-NT:
Table of Contents

Advertisement

UPS5000-H-(1200 kVA-1600 kVA)
User Manual (100 kVA Power Module)
(4) UPS output
Procedure
Step 1 Remove the power distribution cover from the bypass cabinet.
Figure 4-308 Removing the cover
Step 2 Install signal cables inside the cabinets.
Table 4-16 Port mapping table
Cable
Cable 1
Cable 2
Cable 3
Issue 07 (2022-11-29)
Position of Wiring Terminal
1
Cabinet
Power cabinet
1
Power cabinet
1
Power cabinet
1
Copyright © Huawei Digital Power Technologies Co., Ltd.
(5) Bypass input
Port
PU XS1
Signal
One end of
the NTC cable
is preinstalled.
The other end
is reserved
inside the
cabinet and
needs to be
connected to
the bypass
cabinet.
4 Installation and Cable Connection
Position of Wiring Terminal
2
Cabinet
Port
Power cabinet
PU XS1
2
Power cabinet
Signal
2
Bypass
XS5
cabinet
282

Advertisement

Table of Contents
loading

Table of Contents