UPS5000-H-(1200 kVA-1600 kVA)
User Manual (100 kVA Power Module)
Step 4 Secure the cabinet to the channel steel.
Step 5 Install anchor baffle plates around the cabinet.
----End
4.6.3.3 Top Cable Routing or Busway + Top Air Exhaust Configuration
● If the top air-flow cabinet is configured, installation against a wall is supported.
● The following procedure applies to installation against a wall. If cabinets are
Context
Power cabinet 1 is transported separately, and power cabinet 2 and the bypass
cabinet are transported together.
Installation on the Floor
● Ensure that the floor is level.
● The customer needs to purchase the expansion bolts used for securing the
Step 1 Determine the cabinet installation position on the floor based on the mounting
holes in the marking-off template.
Issue 07 (2022-11-29)
NO TE
● In this example, one cabinet is installed not against a wall on C-channel steel with the
openings facing downwards.
● The channel steel model, installation mode, whether holes need to be drilled on a side,
hole size, and the number of cabinets are subject to the site survey data.
NO TICE
not installed against a wall and there is operation space at the rear of the
cabinets, you need to install the cabinet combination screws at the rear and the
anchor screws at the bottom.
NO TICE
cabinet.
Copyright © Huawei Digital Power Technologies Co., Ltd.
4 Installation and Cable Connection
176