4
Insert expansion bolts into the expansion bolt holes in the floor, and tighten the
expansion bolts.
Non-Secured Installation
a.
Wheel the cabinet to the installation position.
b.
Adjust the anchor bolts until the castors hang in the air and the anchor bolts bear
all of the cabinet weight. Check the cabinet levelness using a level instrument.
Combining Cabinets
a.
Install the cabinets one
by one.
b.
Install connecting plates
between cabinets.
If the cabinet is
installed against a
wall, install only the
front connecting
plates.
Installing Cables
1
Remove the cover from the PDU.
2
Remove the top cover from the cabinet based on cable routes and dimensions.
2
3
Install the cables.
The neutral wire needs to be configured for UPS models with N wires.
Communications cable
Nut
4
Set the battery circuit breaker I1.
•
If the load of a single battery cabinet is less than or equal to 150 kW, you are
advised to set the I1 of the battery circuit breaker to MIN and use cables with a
cross-sectional area of 120 mm
2
.
•
If the load of a single battery cabinet is greater than 150 kW, you are advised to
2
use cables with a cross-sectional area of 150 mm
.
Wiring
terminal
Spring washer
Bolt
Flat
washer