5 3 Counterweight Balancing - GE AMX-4+ Technical Manual

Hide thumbs Also See for AMX-4+:
Table of Contents

Advertisement

GE MEDICAL SYSTEMS
REV 5
4 5 3
Counterweight Balancing
Note:
The column assembly trim cover must be removed from top of column assem
bly as shown in Section 4-1.
1. Secure the collimator hand switch closed with a ty wrap or piece of tape to ener
gize the vertical column brake (as well as all other brakes and latch solenoid).
2. With all hardware in place, check the force required to move the tube/arm assem
bly upward and downward. If the force needed to move it up is equal to the force
needed to move it down, the vertical column is balanced. Proceed to Step 5.
3. If the vertical moving forces are unequal, eight oz. (0.23 kg) counterweights (part
number 46-279784P1) should be added or removed (approximately four are in
stalled at the factory).
a.
Move the tube/arm to its lowest possible position. This will raise the counter
poise mass and counterweight to the top of the vertical column where the
counterweight can be accessed.
b. Loosen and remove the two locknuts and washers that hold the counter
weights to the counterpoise.
c.
Add or remove counterweights as required,
d. Replace the washers and locknuts, and tighten locknuts.
4. Repeat Step 2. If the moving forces are equal, proceed to Step 5. If they are still
unequal, repeat Step 3.
5. Replace trim cover on top of vertical column and secure with two hex socket but
ton head capscrews.
4-18
(MODEL 2169360, 2236420 & 2275938 SERIES)
DIRECTION 2173225-100
AMX-4+ SERVICE

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

2169360 series2236420 series2275938 series

Table of Contents