Installing an internal USB device

Installing an internal USB device
Procedure
Procedure
1. If physically powering down a server with the front bezel installed, remove the front bezel .
2. Power down the server.
3. Remove all power:
a. Disconnect each power cord from the power source.
b. Disconnect each power cord from the server.
4. Disconnect all peripheral cables from the server.
5. Remove the server from the rack .
6. Place the server on a flat, level work surface.
7. Remove the access panel .
8. Locate the internal USB port.
9. Remove the riser cage.
10. Plug in the USB device into the USB port.
11. Install the riser cage.
12. Install the access panel .
13. Install the server into the rack .
14. Connect all peripheral cables to the server.
15. Connect the power cords:
a. Connect each power cord to the server.
b. Connect each power cord to the power source.
16. Power up the server .
17. If removed, install the front bezel .
This installation is complete.