Wiring; Flarepro Outside Enclosure And Connections; Standard Compressed Gas Connections - Ametek FlarePro User Manual

Process mass spectrometer
Table of Contents

Advertisement

Figure 3-4.
Communication
ports.

Wiring

All wiring connections for power and signal I/O are made in the terminal box.
Power Requirements:

FlarePro Outside Enclosure and Connections

Standard Compressed Gas Connections

Connect clean, dry compressed air or nitrogen to the port on the top
of the Purge Control Unit. The gas supply must be capable of
supplying 8 SCFM (227 L/m) maximum at 65–100 PSIG (5.4 to 6.8
BARG). Fitting is 1/4" NPTF. This supplies gas to the purge /
pressurization system as well as supplying gas to control the
pneumatic valve inlets.
3-6 | FlarePro Process Mass Spectrometer
RS-485
Network Setting Switch
Connect 9-pin,DB-9
male connector
Switch between
RS-232 and RS-485
110–127 VAC, 50/60 Hz, 1000 W max.
220–240 VAC, 50/60 Hz, 1000 W max.
The unit can be purged with clean, dry compressed air or nitrogen.
Ensure that the Purge Gas Toggle Switch is in the ON position to
allow gas to enter the enclosure.
RS-485
RS-
RS-
485
485
RS-
232

Advertisement

Table of Contents
loading

Table of Contents