Commissioning and configuring

6.9 Series commissioning

6.9
Series commissioning
A loaded project that has been commissioned, can be loaded to another SINUMERIK MC,
while still keeping the Safety parameterization. However, observe the following information:
● Different component checksums as a result of series commissioning with Safety Integrated
functionality (Page 348)
● Safety message for series commissioning with third-party motor (see below)
For series commissioning, you must perform an acceptance test (Page 341) for each
SINUMERIK MC.
Safety message for standard commissioning with Safety Integrated Extended Functions
If third-party motors with absolute encoders are being used, a situation may occur, where a
safety message prevents commissioning.
One reason for this may be that a different serial number of the absolute encoder is saved on
the memory card than that in the Control Unit that is to be commissioned. The safety message
can only be acknowledged once the serial number for the absolute encoder has first been
manually corrected. You can then carry on with the commissioning.