Checking The Load Operation; Loading The Configuration To The Pc System - Siemens SINUMERIK MC Commissioning Manual

Safety integrated (with sinamics s120)
Hide thumbs Also See for SINUMERIK MC:
Table of Contents

Advertisement

Result
The PLC is stopped and the configuration is loaded to the PLC.
The "Results of the loading action" dialog opens and displays the status of the loading action.
The dialog restarts the PLC after completion, provided the "Start" checkbox has not been
deactivated.
6.4.2

Checking the load operation

Checking the load operation
If several MCUs/PLCs can be accessed from a PG/PC via a network, you must check to ensure
that the project data were loaded to the correct PLC. The simplest way of doing this check is to
compare the F-signature at the PG/PC with the F-signature in the PLC. If the F-collective
signature is identical, then you have loaded the project data to the correct PLC.
1. Call menu "Safety administration" in the TIA Portal. To the right in the secondary navigation,
select menu "General".
2. In the SINUMERIK ONE Commissioning Tool, call screen form "SI checksums overview" for
the selected PLC.
MENU SELECT > Diagnostics > Menu forward key > Safety > SI checksums (> global
checksums)
3. Compare the F-collective signature in the TIA Portal (PG/PC) with the F-collective signature
in the SINUMERIK ONE Commissioning Tool (PLC).
6.4.3

Loading the configuration to the PC system

Preconditions
● The hardware configuration is compiled (Page 45).
● A communication connection (Page 45) exists between the PG/PC (TIA Portal) and the PC
system.
Safety Integrated (with SINAMICS S120)
Commissioning Manual, 02/2020, A5E46305916B AB
Commissioning and configuring
6.4 Load the configuration into the control system
245

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents