2. Commissioning

2.1 Preparing the CP system for operation on the INTERBUS

2.1.1 Operating voltage

PLEASE NOTE
• The CP fieldbus node must have a separate
The operating voltage for the remote bus/installation
remote bus is not used by the CP system. This volt-
age is looped through in order to supply further
INTERBUS slaves.

2.1.2 Saving the string assignment

PLEASE NOTE
Before commissioning the CP system, you must first
prepare the CP system (see "CP System" manual).
Before commissioning the CP system on the
INTERBUS, proceed as follows:
1. Connect the operating voltage for the node
2. Connect the CP modules.
3. Switch on the operating voltage.
4. Save the string assignment by pressing the SAVE
5. Switch off the operating voltage for the node.
CP FB6-E 9809c
operating voltage supply.
(see "CP system" manual).
button.
2-3