ABB Relion 670 Series Commissioning Manual page 263

Line distance protection
Hide thumbs Also See for Relion 670 Series:
Table of Contents

Advertisement

1MRK 506 371-UUS E
Section 13
13.1
Commissioning tests
During commissioning all protection functions shall be verified with the setting values used at
each plant. The commissioning tests must include verification of all circuits by highlighting the
circuit diagrams and the configuration diagrams for the used functions.
Further, the settings for protection functions are tested and recorded carefully as outlined for the
future periodic maintenance tests.
The final testing includes primary verification of all directional functions where load currents is
checked on the local HMI and in PCM600. The magnitudes and angles of all currents and voltages
should be checked and the symmetry verified.
Directional functions have information about the measured direction and, for example, measured
impedance. These values must be checked and verified as correct with the export or import of
power available.
Finally, final trip tests must be performed. This involves activation of protection functions or
tripping outputs with the circuit breaker closed and the tripping of the breaker verified. When
several breakers are involved, each breaker must be checked individually and it must be verified
that the other involved breakers are not tripped at the same time.
13.2
Periodic maintenance tests
The periodicity of all tests depends on several factors, for example the importance of the
installation, environmental conditions, simple or complex equipment, static or electromechanical
IEDs, and so on.
The normal maintenance practices of the user should be followed. However, ABB's
recommendation is as follows:
Every second to third year
Visual inspection of all equipment.
Removal of dust on ventilation louvres and IEDs if necessary.
Periodic maintenance test for protection IEDs of object where no redundant protections are
provided.
Every four to six years
Periodic maintenance test for protection IEDs of objects with redundant protection system.
Line distance protection REL670
Commissioning manual
Commissioning and maintenance of
the fault clearing system
First maintenance test should always be carried out after the first half year of
service.
© Copyright 2017 ABB. All rights reserved
Commissioning and maintenance of the fault clearing system
Section 13
SEMOD56513-5 v5
SEMOD56517-1 v1
SEMOD56520-5 v4
257

Advertisement

Table of Contents
loading

This manual is also suitable for:

Rel670

Table of Contents