Section 11
Testing functionality by secondary injection
setting 2.0s) and shorter than the dead-time of SMBRREC (79), when included in the
protection scheme.
7.
Check, that the output signals, issued for the first fault, correspond to a two-phase trip for
included phases. The output signals generated by the second fault must correspond to the
three-phase tripping action.
11.12.1.4
Circuit breaker lockout
The following tests should be carried out when the built-in lockout function is used in addition to
possible other tests, which depends on the complete configuration of an IED.
1.
Check that
2.
Activate shortly the set lockout (SETLKOUT) signal in the IED.
3.
Check that the circuit breaker lockout (CLLKOUT) signal is set.
4.
Activate shortly thereafter, the reset lockout (RSTLKOUT) signal in the IED.
5.
Check that the circuit breaker lockout (CLLKOUT) signal is reset.
6.
Initiate a three-phase fault.
A three- trip should occur and all trip outputs TR_A, TR_B, TR_C should be activated.
Functional outputs TRIP and TR3P should be active at each fault. The output CLLKOUT should
not be set.
7.
Activate the automatic lockout function, set
Besides the TRIP outputs, CLLKOUT should be set.
8.
Reset the lockout signal by activating the reset lockout (RSTLKOUT) signal.
9.
Activate the trip signal lockout function, set
All trip outputs (TR_A, TR_B, TR_C) and functional outputs TRIP and TR3P must be active and
stay active after each fault, CLLKOUT should be set.
10.
Reset the lockout.
All functional outputs should reset.
11.
Deactivate the trip signal lockout function, set
lockout function, set
11.12.1.5
Completing the test
continue to test another function or end the test by changing the
Restore connections and settings to their original values, if they were changed for testing
purposes.
11.13
Monitoring
11.13.1
Gas medium supervision SSIMG
Prepare the IED for verification of settings as outlined in Section
settings"
Values of logical signals for SSIMG protection are available on the local HMI under Main menu/
Tests/Function status/Monitoring/InsulationGas(63)/SSIMG(63):x, where x = 1, 2,....21.
The Signal Monitoring in PCM600 shows the same signals that are available on the local HMI.
Check that the input logical signal BLOCK is logical zero and that on the local HMI, the logical
signals PRESALM, PRESLO, TEMPALM, TEMPLO, ALARM and LOCKOUT are logical zero.
240
AutoLock and TripLockout are both set to Disabled .
AutoLock = Disabled .
in this chapter.
© Copyright 2017 ABB. All rights reserved
AutoLock = Enabled and repeat.
TripLockout = Enabled and repeat.
TripLockout = Disabled and the automatic
TESTMODE setting to Disabled .
"Preparing the IED to verify
Line distance protection REL670
1MRK 506 371-UUS E
SEMOD54375-170 v11
SEMOD54375-203 v6
SEMOD53581-1 v1
GUID-0A83B4D5-51FF-43CB-8DC7-AFCEA2BC7B69 v3
Commissioning manual

Advertisement

Table of Contents
loading

This manual is also suitable for:

Rel670

Table of Contents