Section 11
Testing functionality by secondary injection
4.
Change the angle between the injected current and voltage back to 0°. Decrease the current
slowly until the PICKUP1 signal, pickup of stage 1, is activated.
5.
Increase the current to 100% of
6.
Switch the current off and measure the time for activation of TRIP1, trip of stage 1.
7.
If a second stage is used, repeat steps
11.5.11.2
Completing the test
continue to test another function or end the test by changing the
Restore connections and settings to their original values, if they were changed for testing
purposes.
11.5.12
Directional overpower protection GOPPDOP (32)
Prepare the IED for verification of settings as outlined in section
section
"Preparing for test"
11.5.12.1
Verifying the settings
The overpower protection shall be set to values according to the real set values to be used. The
test is made by means of injection of voltage and current where the amplitude of both current and
voltage and the phase angle between the voltage and current can be controlled. During the test
the analog outputs of active and reactive power shall be monitored.
1.
Connect the test set for injection of voltage and current corresponding to the mode to be
used in the application. If a three phase test set is available this could be used for all the
modes. If a single phase current/voltage test set is available the test set should be
connected to a selected input for one phase current and voltage.
2.
Adjust the injected current and voltage to the set rated values in % of
(converted to secondary current and voltage). The angle between the injected current and
voltage shall be set equal to the set direction
forward power protection and equal to 180° for reverse power protection). Check that the
monitored active power is equal to 100% of rated power and that the reactive power is equal
to 0% of rated power.
3.
Change the angle between the injected current and voltage to
monitored active power is equal to 0% of rated power and that the reactive power is equal to
100% of rated power.
4.
Change the angle between the injected current and voltage back to
current slowly from 0 until the PICKUP1 signal, pickup of stage 1, is activated. Check the
injected power and compare it to the set value
Sbase .
5.
Increase the current to 100% of
6.
Switch the current on and measure the time for activation of TRIP1, trip of stage 1.
7.
If a second stage is used, repeat steps
11.5.12.2
Completing the test
continue to test another function or end the test by changing the
Restore connections and settings to their original values, if they were changed for testing
purposes.
178
IBase .
2
to
in this chapter.
IBase and switch the current off.
2
to
© Copyright 2017 ABB. All rights reserved
6
for the second stage.
TESTMODE setting to Disabled .
"Requirements"
Angle1 , angle for stage 1 (equal to 0° for low
Angle1 + 90°. Check that the
Power1 , power setting for stage 1 in % of
6
for the second stage.
TESTMODE setting to Disabled .
Line distance protection REL670
1MRK 506 371-UUS E
SEMOD175027-15 v4
SEMOD175058-3 v5
and
SEMOD175058-7 v6
IBase and VBase
Angle1 value. Increase the
SEMOD175058-66 v4
Commissioning manual

Advertisement

Table of Contents
loading

This manual is also suitable for:

Rel670

Table of Contents