ABB Relion 670 Series Commissioning Manual page 10

Line distance protection
Hide thumbs Also See for Relion 670 Series:
Table of Contents

Advertisement

Table of contents
11.4.3.2
Phase-to-ground faults............................................................................................................... 109
11.4.4
Faulty phase identification with load encroachment FMPSPDIS (21).................................... 110
11.4.5
Distance protection zones, quadrilateral characteristic, separate settings ZMRPDIS
(21)....................................................................................................................................................... 110
11.4.5.1
Measuring the operating limit of set values............................................................................ 114
11.4.5.2
Measuring the operating time of distance protection zones.............................................. 114
11.4.6
Phase selection, quadrilateral characteristic with settable angle FRPSPDIS (21)............... 115
11.4.6.1
Measuring the operating limit of set values............................................................................ 117
11.4.6.2
Completing the test...................................................................................................................... 117
11.4.7
High speed distance protection zones, quadrilateral and mho characteristic
ZMFPDIS (21)......................................................................................................................................118
11.4.7.1
Measuring the operating limit of set values............................................................................ 121
11.4.7.2
Measuring the operating time of distance protection zones.............................................. 122
11.4.7.3
Completing the test......................................................................................................................122
11.4.8
High Speed distance for series compensated line zones, quadrilateral and mho
characteristic ZMFCPDIS (21).........................................................................................................122
11.4.8.1
Measuring the operating limit of set values............................................................................125
11.4.8.2
Measuring the operating time of distance protection zones..............................................126
11.4.8.3
Transient directional element.................................................................................................... 126
11.4.8.4
Completing the test..................................................................................................................... 126
11.4.9
Power swing detection ZMRPSB (68)........................................................................................... 127
11.4.9.1
Verifying the signal and settings............................................................................................... 127
11.4.9.2
Completing the test......................................................................................................................133
11.4.10
Power swing logic PSLPSCH...........................................................................................................133
11.4.10.1
Testing the carrier send and trip signals................................................................................. 133
11.4.10.2
Testing the influence of the residual overcurrent protection............................................. 134
11.4.10.3
Checking the underreaching zone............................................................................................. 134
11.4.10.4
Completing the test..................................................................................................................... 134
11.4.11
Pole slip protection PSPPPAM (78)............................................................................................... 135
11.4.11.1
Verifying the settings...................................................................................................................135
11.4.11.2
Completing the test......................................................................................................................137
11.4.12
Out-of-step protection OOSPPAM................................................................................................137
11.4.12.1
Verifying the settings...................................................................................................................138
11.4.12.2
Test of point RE (R
11.4.12.3
Test of the boundary between zone 1 and zone 2, which is defined by the
parameter
11.4.12.4
Test of the point SE (R
11.4.13
Automatic switch onto fault logic ZCVPSOF..............................................................................154
11.4.13.1
Activating ZCVPSOF externally.................................................................................................. 154
11.4.13.2
Initiating ZCVPSOF automatically and setting mode to impedance................................. 155
11.4.13.3
Initiating ZCVPSOF automatically and setting mode to VILevel ........................................ 155
11.4.13.4
Completing the test..................................................................................................................... 155
11.4.14
Phase preference logic PPLPHIZ .................................................................................................. 155
4
, X
)................................................................................................... 142
FwdR
FwdX
ReachZ1 ...................................................................................................................... 146
, X
).............................................................................................. 150
RvsR
RvsX
© Copyright 2017 ABB. All rights reserved
Line distance protection REL670
Commissioning manual

Advertisement

Table of Contents
loading

This manual is also suitable for:

Rel670

Table of Contents