Section 11
Testing functionality by secondary injection
Means to indicate, measure and record operation and times, for example an event recording
facility
A bi-stable relay (BR) or two auxiliary relays to simulate a CB
Two push-buttons (SC, ST) to operate the BR and a change-over switch (SRY) to simulate
CBREADY
Possibly a switch simulation the synchronizing check SESRSYN (25) condition
To test
set
-
ANSI04000202 V2 EN-US
Figure 54: Simulating the CB operation by a bi-stable relay/breaker simulator and manual
11.10.2.1
Preparation of the verification
1.
Check the function settings on the local HMI under Main menu/Settings/IED Settings/
Control/Autorecloser79,5(0–>1)/SMBRREC:x(79,5(0–>)):x
216
BI
BI
ST
SRY
switches
© Copyright 2017 ABB. All rights reserved
SC
BR
ANSI04000202-1-en.vsd
1MRK 506 371-UUS E
M12400-40 v8
Line distance protection REL670
Commissioning manual

Advertisement

Table of Contents
loading

This manual is also suitable for:

Rel670

Table of Contents