Chapter 3 - Commissioning
3.2

Operation Verification

The following sections describe how to verify the correct functioning of the
Outdoor Units, Indoor Units, Ethernet connection and data connectivity.
3.2.1.1
AU-ODU LEDs
To verify the correct operation of the AU-ODU, examine the LED indicators
located on the bottom panel of the outdoor unit.
The following tables list the provided LEDs and their associated indications.
NOTE
Verifying the correct operation of the Outdoor Unit using the LEDs, as described below, is only
possible after the configuration of basic parameters has been completed.
Name
PWR
ALARM
ETH
(WLNK)
52

Table 3-2: AU-ODU LEDs

Description
Power indication
Not Used
Wireless link status indication
WILINK I MODULAR BASE STATION SYSTEM MANUAL
Functionality
Off – ODU is not powered
Green – ODU power is OK
(Red – blinks shortly during ODU power up)
Off – No SU is associated
Green – At least one SU is associated