Figure 6-14 Removing the old Gold power supply module
Step 4 Insert the new power supply module into the subrack until the ejector lever is locked and the
bottom is reached.
Step 5 Connect the power cable to the new power supply module.
Step 6 If the running status indicator is steady green, the new power supply module works properly.
----End

6.4.3.3 Replacing a VCN540

Prerequisites
Impact on the System
Videos cannot be recorded during the replacement of the VCN540.
Issue 04 (2020-03-25)
Tools: Phillips screwdriver
A spare VCN540 of the same model is available and functional.
Copyright © Huawei Technologies Co., Ltd.
6 Parts Replacement
55

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the FusionModule5000 Smart Modular Data Center and is the answer not in the manual?

Subscribe to Our Youtube Channel

This manual is also suitable for:

V100r003c00

Table of Contents