Replacing A Vcn500 Gold Power Supply Module - Huawei FusionModule5000 Smart Modular Data Center Maintenance Manual

Hide thumbs Also See for FusionModule5000 Smart Modular Data Center:
Table of Contents

Advertisement

SmartDC
Maintenance Guide
Figure 6-13 Installing a new hard drive
Step 4 Observe the hard drive indicator to check whether the hard drive works properly.
----End

6.4.3.2 Replacing a VCN500 Gold Power Supply Module

Prerequisites
The installation position of the new Gold power supply module has been specified.
Procedure
Step 1 Put on an ESD wrist strap (or ESD gloves) and insert the ground terminal into the ESD jack in
the cabinet.
Step 2 Remove the power cable from the old Gold power supply module.
Step 3 Remove the old Gold power supply module.
1.
2.
Issue 04 (2020-03-25)
Hold the handle of the power supply module and push the ejector lever towards the
handle.
Hold the bottom of the power supply module and slowly pull the power supply module
out.
Copyright © Huawei Technologies Co., Ltd.
6 Parts Replacement
54