Figure 6-9 Removing the ECC800-Pro main control module
Step 4 Remove the SIM card and micro SD card from the card slot.
Figure 6-10 Removing a SIM card and a micro SD card
Step 5 Install the spare SIM card and micro SD card into the card slot.
Figure 6-11 Installing a SIM card and a micro SD card
Step 6 Install the ECC800-Pro main control module in the card slot.
Step 7 Tighten the screws on both sides of the ECC800-Pro main control module.