Chapter 4 Procedure Before Operation; Procedure Before Operation - Mitsubishi Electric MELSEC SW1DNC-CCIEF-B User Manual

Cc-link ie field network interface board
Table of Contents

Advertisement

4

PROCEDURE BEFORE OPERATION

4.1
Procedure Before Operation
This section explains the procedure before operating the CC-Link IE Field Network board.
Install the software package on a personal computer.
Page 80 Installation
Install the board to a slot on the personal computer.
Page 45 Board installation
Set the channel number and confirm it with the utility.
Page 46 Setting Channel Numbers
Test the hardware of the installed board.
Page 47 Tests Before Wiring (Standalone Tests of the Board)
Wire the network cables for the installed board.
Page 50 Wiring
Set the parameters and check them with the utility.
Page 98 SETTING PARAMETERS
Test the cable connection and data link on the network.
Page 54 Tests After Wiring
Execute a user program or utility.
4 PROCEDURE BEFORE OPERATION
40
4.1 Procedure Before Operation
Start
Install the software package
Install the board
Set the channel number
Check the board
Wire the cables
Set the parameters
Check the network
Execute a user program
End
Check

Hide quick links: