6 PROCEDURE AND SETTINGS UP TO THE POINT OF OPERATION
6 PROCEDURE AND SETTINGS UP TO THE POINT OF OPERATION
This section explains the operating procedure up to the point the MELSECNET/H
board is operated.
6.1 Procedure Up to the Point of Operation
An outline of the procedure up to the point of MELSECNET/H board operation is
explained below.
Check
□
Install the software package on a personal computer.
□
Install the board to a slot on the personal computer.
For the board with external power supply function, wire the
external power supply cable.
□
Set the channel No. and confirm it with the utility.
□
Test the hardware of the installed board.
□
Wire the network cables for the installed board.
□
Set the parameters and confirm them with the utility.
□
Test the cable connection and data link on the network.
□
Execute a user program or utility.
6 - 1
Start
↓
Install the software package
↓
Install the board
↓
Set the channel No.
↓
Check the board
↓
Wire the cables
↓
Set the parameters
↓
Check the network
↓
Execute a user program
↓
Operation
REMARK
It is necessary to perform settings on the control station side in order to use the
MELSECNET/H board as a normal station. Set the control station side as required.
Refer to manuals listed below for the setting on the control station side.
• Q Corresponding MELSECNET/H Network System Reference Manual (PLC to
PLC network)
• For QnA/Q4AR MELSECNET/10 Network System Reference Manual
MELSEC
• • • Section 8.2 Installation
• • • Section 6.3.3 Board installation
• • • Section 6.4.4 External power
supply cable wiring
• • • Section 6.3.4 Channel No. settings
• • • Section 6.5 Test
• • • Section 6.4 Wiring
• • • Chapter 7 PARAMETER SETTINGS
• • • Section 6.5 Test
6