Commissioning; Function Check; Switching On The Measuring Device - Endress+Hauser Proline Prosonic Flow 93 Operating Instructions Manual

Foundation fieldbus ultrasonic flow measuring system
Hide thumbs Also See for Proline Prosonic Flow 93:
Table of Contents

Advertisement

Proline Prosonic Flow 93 FOUNDATION Fieldbus
!
!
Endress+Hauser
6

Commissioning

6.1

Function check

Make sure that the following function checks have been performed successfully before switching on
the supply voltage for the measuring device:
• Checklist for "Post-installation check"  ä 57
• Checklist for "Post-connection check"  ä 68
Note!
• The FOUNDATION FIELDBUS interface's technical data must be maintained in accordance with
IEC 61158-2 (MBP).
• A normal multimeter can be used to check the bus voltage of 9 to 32 V and the current
consumption of 11 mA at the device (FF interface).
6.2

Switching on the measuring device

Once the function check has been performed successfully, the device is operational and can be
switched on via the supply voltage. The device then performs internal test functions and the
following messages are shown on the local display:
PROSONIC FLOW 93
START-UP
RUNNING
Æ
PROSONIC FLOW 93
DEVICE SOFTWARE
V XX.XX.XX
Æ
FOUND. FIELDBUS
Æ
SYSTEM OK
 OPERATION
Normal measuring mode commences as soon as startup completes.
Various measured value and/or status variables appear on the display (HOME position).
Note!
If startup fails, an appropriate error message is displayed, depending on the cause.
Startup message
Current software version
Software
Existing input/output modules
Input/output modules
Beginning of normal
measuring mode
Commissioning
79