Commissioning

10.1

Post-mounting and post-connection check

Before commissioning the device:
Make sure that the post-installation and post-connection checks have been performed
successfully.
• Checklist for "Post-mounting" check→  43
• Checklist for "Post-connection check" →  64
10.2

Preparatory steps

The device can only be operated via the SmartBlue App.
10.2.1

Install the SmartBlue App

Download the SmartBlue App →  66
10.2.2

Connect the SmartBlue App to the device

Log in →  67
10.3

Configuring the measuring device

Complete this wizard to commission the device.
For each parameter, enter the appropriate value or select the appropriate option.
NOTE
If you exit the wizard before completing all required parameters, the changes you have
made will be saved. For this reason, the device may then be in an undefined state!
In this case, a reset to the default settings is recommended.
1. Open the Guidance menu.
2. Start the Commissioning wizard.
3. Follow the instructions in the SmartBlue App.
 The configuration is completed.
10.4

Protecting settings from unauthorized access

The following options exist for protecting the configuration of the measuring device from
unintentional modification after commissioning:
• Write protection via access code →  69
• Write protection via write protection switch →  11
10.4.1

Write protection via access code

The effects of the user-specific access code are as follows:
Via the SmartBlue App, the parameters for the measuring device configuration are write-
protected and their values can no longer be changed.
Commissioning