Wiring
68
4.5

Post-connection check

Perform the following checks after completing electrical installation of the measuring device:
Device condition and specifications
Are cables or the device damaged (visual inspection)?
Electrical connection
Does the supply voltage match the specifications on the nameplate?
Do the cables comply with the specifications?
Do the cables have adequate strain relief?
Is the cable type route completely isolated?
Without loops and crossovers?
Are the power supply and signal cables correctly connected?
Are all screw terminals firmly tightened?
Are all cable entries installed, firmly tightened and correctly sealed?
Cables looped as "water traps"?
Are all the housing covers installed and tightened?
Electrical connection of FOUNDATION Fieldbus
Are all the connecting components (T-boxes, junction boxes, connectors, etc.)
connected with each other correctly?
Has each fieldbus segment been terminated at both ends with a bus terminator?
Has the max. length of the fieldbus cable been observed in accordance with the
FOUNDATION Fieldbus specifications?
Has the max. length of the spurs been observed in accordance with the
FOUNDATION Fieldbus specifications?
Is the fieldbus cable fully shielded (90%) and correctly grounded?
Proline Prosonic Flow 93 FOUNDATION Fieldbus
Notes
-
Notes
85 to 260 V AC (45 to 65 Hz)
20 to 55 V AC (45 to 65 Hz)
16 to 62 V DC
 ä 58
-
-
See the wiring diagram inside
the cover of the terminal
compartment
-
 ä 67
-
Notes
-
-
 ä 59
 ä 59