Process Pressure Checks; Cell Checks - Ametek Thermox Series 2000 WDG-IV User Manual

Table of Contents

Advertisement

Process Pressure Checks

To check that you entered the process pressure correctly, select Process Pressure from the
Setup key. Also ensure that the calibration process pressure equals normal operating process
pressure. Calibration should only be performed under these conditions for highest accuracy.

Cell Checks

If the cell fails when you first begin
to use the analyzer:
If the analyzer has been operating
for some time and you feel the oxy-
gen reading is inaccurate:
If your analyzer doesn't respond
properly to the calibration gas:
If this doesn't solve the problem, replace the cell, then run another primary calibration.
6-10 | Thermox Series 2000 WDG-IV / IVC / IVCM
It is likely that there is a leak in the sensor plumbing
or an improper calibration gas setup, and there is not
a problem with the cell itself (see the "Leak Check"
section later in this chapter for help on how to check
for leaks; see the "Calibration/Aspirator Air Checks"
section earlier in this chapter for help on checking
your calibration gas setup).
First check by running a known calibration gas to veri-
fy the analyzer's response. If the analyzer responds to
the calibration gas correctly, it indicates either leaking
or plugged plumbing.
This may indicate a problem with the cell. Before
replacing the cell, put the analyzer through a primary
calibration and see if this improves the response of
the analyzer. If this doesn't work, check for leaks or
plugged plumbing.

Advertisement

Table of Contents
loading

Table of Contents