PTX10001-36MR Site Preparation Checklist

The checklist in
Table 21 on page 47
for a PTX10001-36MR installation.
Table 21: Site Preparation Checklist
Item or Task
Environment
Verify that environmental factors such as
temperature and humidity do not exceed
router tolerances.
Power
Measure the distance between external
power sources and the router installation
site.
Calculate the power consumption and
requirements.
Rack or Cabinet
Verify that your rack or cabinet meets the
minimum requirements for the installation of
the router.
Plan rack or cabinet location, including
required space clearances.
Secure the rack or cabinet to the floor and
building structure.
summarizes the tasks you need to perform when preparing a site
For More Information
"PTX10001-36MR Environmental
Requirements and Specifications" on
page 49
Table 12 on page 30
Table 14 on page 31
"PTX10001-36MR Rack Requirements"
on page 54
"PTX10001-36MR Clearance
Requirements for Airflow and Hardware
Maintenance" on page 52
Performed by
Date
47