Eaton Powerware 9390 Installation And Operation Manual page 36

20-80kva
Hide thumbs Also See for Powerware 9390:
Table of Contents

Advertisement

INSTALLING THE UPS SYSTEM
4-10
EATON Powerware
12. Remove the screws securing the bottom internal safety shield panel and remove
the panel to gain access to the bottom conduit landing plate.
NOTE When installing UV trip and Aux battery interface wiring to the UPS interface terminals, conduit
must be installed between the UPS and battery cabinets.
13. Remove the UPS cabinet top or bottom conduit landing plate to drill or punch
conduit holes (see Drawing 164201603-6 on page A-34).
14. Reinstall the conduit landing plate and install the conduit.
15. Route the UV trip and Aux wiring from the battery cabinet to the UPS.
16. Connect the wiring to the TB1 terminals.
17. If wiring X-Slot connections, proceed to paragraph 4.8.3; otherwise, proceed to
Step 18.
18. When all wiring is complete, reinstall the safety shield panels removed in
previous steps. Secure with the retained hardware.
19. Close the control panel door and secure with the retained hardware.
20. Reinstall the door removed in Step 3 or paragraph 4.2 and secure with the
retained hardware.
21. Close the door and secure the latch.
4.8.3
X-Slot Connections
NOTE LAN and telephone drops for use with X-Slot connectivity cards must be provided by facility planners
or the customer.
NOTE When installing external wiring to X-Slot cards, conduit must be installed to the UPS cabinet. When
installing internal wiring to X-Slot terminals, route the wiring through the internal opening in the X-Slot
communication bay.
For installation and setup of an X-Slot card, please contact Eaton (see page 1-7).
To install wiring for connections:
1.
If not already installed, install the LAN and telephone drops.
2.
Unfasten the front door latch and swing the door open.
3.
Remove the UPS cabinet X-Slot conduit landing plate to drill or punch conduit
holes (see Drawing 164201603-6 on page A-34).
4.
Reinstall the conduit landing plate and install the conduit.
5.
Route and install the LAN, telephone, and other cables to the appropriate X-Slot
cards.
6.
When all wiring is complete, reinstall the safety shield panels removed in
previous steps. Secure with the retained hardware.
7.
Close the control panel door and secure with the retained hardware.
®
9390 UPS (20–80 kVA) Installation and Operation Manual
S
164201603 Rev 2 www.powerware.com

Advertisement

Table of Contents
loading

Table of Contents