UTILITY GRID INTERCONNECTION
Utility Connection Requirements
Review all applicable national or local codes for specific requirements for the size of
the electrical service and the amount of current that is allowed to be fed into the panel
by the inverter.
Contacting Your Local Utility
Contact your electrical utility before connecting the inverter to ensure there are no
local restrictions or special requirements. Your local utility company may require
specific inspections, equipment, or other procedures not covered in this document.
Voltage Output
This inverter is designed to be connected to a three phase, grounded, wye
transformer. The AC output voltage is available on the inverter data plate for the
output voltage wye configuration. Do not change the output voltage of the inverter.
AC and DC power requirements are included in the specifications.
Related Links
• "Specifications" on page 9-1
INVERTER MONITORING
The inverter is equipped with a data monitoring module that can be used to monitor
the inverter through one of the following interfaces:
• Basic performance data can be accessed using a free web-based monitoring
service provided by AE.
• Locally through a third party monitoring system using Modbus/TCP or
Modbus/RTU.