3. Check the screens at the bottom of the compartment for damage or debris.
4. Replace the cover plates. Make sure the gaskets are not damaged during
replacement of the plates. Do not overtighten the screws.
Step 3: AC and DC Sub Panel Compartments
1. Check the integrity of the bus bar connections and terminals for each bus bar
landing in the AC and DC compartments.
Figure 4‑6. Bus bar connection inspection
2. Ensure the cable connections are plugged in and fully seated.
3. Inspect and pull test all cable screw terminal connections.
570-1001791-05A
Advanced Energy® AE 500 Inverter
Connection inspection
Installing
4‑7