ControlWave I/O Expansion Rack Instruction Manual
Test Procedure
5-30
Use this procedure to test the comm ports.
Connect an external loop-back plug to the port on the CPU or
1.
SCB port you want to test. Valid ports are:
J2 of CPU board for COM1
J3 of CPU board for COM2
J2 of SCB board for COM3
J3 of SCB board for COM4
Select Communications on the WINDIAG Main Diagnostics
2.
Menu. The Communications Diagnostic screen opens:
Figure 5-24. Communications Diagnostic Menu
Enter 5 in the Number of Passes field.
3.
Select a port to test (click  to display all available ports).
4.
: The port you select must correlate to the port on which you
Note
placed the loop-back plug in step 1.
Select 115200 or ALL ASYNC as the baud rate (click  to
5.
display all available rates).
Click RUN to start the test. At the completion of the test (which
6.
generally takes about 5 seconds), any failed results appear in the
Status field to the right of the RUN button:
TXD RXD Failure
CTS RTS Failure
Click Return to Menu to display the WINDIAG Main Menu.
7.
Service & Troubleshooting