Siemens GCP5000 Instruction & Installation Manual page 215

Grade crossing predictor for electrified territory (gce)
Table of Contents

Advertisement

_________________________________________________________________________________________________________
4.5 Installation
4.5.1 Crossing Controller Module Installation
Two non-redundant A80405 Solid-State Crossing Controller IIIi (SSCC IIIi) modules can be
installed in the GCP5000 (GCE) as shown in Figure 4-7. Crossing Controller lamp and bell
circuit wiring include:
Installation of wiring between the GCP5000 (GCE) Crossing Controller connectors
and the SSCC III Lighting Surge Panels
Installation of underground wiring between the SSCC III Lighting Surge Panels and
the crossing Mast Junction Boxes
Use of SSCC III Lighting Surge Panel(s)
Where one signal is controlled by each Controller Module, one surge panel may be used for
both modules as shown in Figure 4-8.
WHEN ONE FLASHING LIGHT SIGNAL IS CONTROLLED BY EACH
SSCC MODULE, A SINGLE SURGE PANEL MAY BE USED AS
SHOWN IN FIGURE 4-8. JUMPER LINKS FROM A TO B MUST BE
REMOVED IN TWO PLACES.
WHERE TWO SIGNALS ARE CONTROLLED BY A SINGLE
CROSSING CONTROLLER MODULE, ONE SURGE PANEL MAY BE
USED AS SHOWN IN FIGURE 4-9
Where multiple signals are controlled by each Crossing Controller
Module, an additional –2 surge panel is required and is wired and jumper
links installed similar to Figure 4-9, but connected to the second SSCC
module connector.
SIG-00-22-02
Version: B.1
SSCC APPLICATIONS & PROGRAMMING GUIDELINES
WARNING
NOTE
4-11
JUNE 2022 (Revised September 2022)