Temperature And Humidity Guidelines; Power Connection Guidelines - Cisco 12416 Installation And Configuration Manual

Cisco systems bridge/router installation and configuration guide
Hide thumbs Also See for Cisco 12416:
Table of Contents

Advertisement

Chapter 2
Preparing for Installation

Temperature and Humidity Guidelines

Power Connection Guidelines

Caution
OL-11495-01
The operating and nonoperating environmental site requirements are listed in
Table A-4 on page
A-4. The router normally operates within the ranges listed in
Table A-4, however, if a temperature measurement is approaching a minimum or
maximum parameter it indicates a potential problem. Maintain normal operation
by anticipating and correcting environmental anomalies before they approach
critical values by properly planning and preparing your site before you install the
router.
You can configure the router with either an AC-input or DC-input power
subsystem, so the site power source requirements differ depending on the power
subsystem in your router. Ensure all power connection wiring conforms to the
rules and regulations in the National Electrical Code (NEC), as well as local
codes.
Proper grounding is necessary to avoid damage from lightning and power surges.
See the
"Router Bonding and Grounding Receptacles—Top Rear" section on
page 2-23
for grounding requirements.
Cisco 12016, Cisco 12416, and Cisco 12816 Router Installation and Configuration Guide
Site Requirement Guidelines
2-17