Removing and Installing a Chassis
Step 7
Figure 7-56 Closing the Scissor-Jack Platform to Lower the Chassis
Front of chassis
Scissor-jack
screw
Counter-clockwise
expands platform
Step 8
Cisco 12016, Cisco 12416, and Cisco 12816 Router Installation and Configuration Guide
7-96
Turn the scissor-jack screw clockwise to slowly lower the scissor-jack platform
(Figure
7-56).
Slide the chassis and scissor-jack platform onto a safety hand truck with outrigger
wheels and secure it with the locking safety strap.
Move the chassis to a level solid floor where the chassis can be
repackaged for shipping.
Use the packaging and unpacking instructions that came with the
replacement chassis to repack and ship a defective chassis to the factory.
Chassis anchor
clip and bolt
(2 on each side)
Clockwise
closes platform
Chapter 7
Maintaining the Router
Scissor-jack
platform