COMMISSIONING

Please make the under procedures checking before commissioning,
1. Ensure all the connections are correct and wires diameter is suitable.
2. Ensure that the controller DC power has fuse, controller's positive and negative
connected to start battery are correct.
3. Emergence stop must be connected with positive of start battery via scram button's
normal close point and fuse.
4. Take proper action to prevent engine to crank disconnect (e. g. Remove the connection
wire of fuel valve). If checking is OK, make the start battery power on; choose manual
mode and controller will executive routine.
5. Set controller under manual mode, press "start" button, genset will start. After the setting
times as setting, controller will send signal of Start Fail; then press "stop" to reset
controller.
6. Recover the action of stop engine start (e. g. Connect wire of fuel valve), press start
button again, genset will start. If everything goes well, genset will normal run after idle
running (if idle run be set). During this time, please watch for engine's running situations
and AC generator's voltage and frequency. If abnormal, stop genset running and check
all wires connection according to this manual.
7. If there is any other question, please contact Smartgen's service.