COMMISSIONING

It is recommended that the following checks are made before starting the system:
1)
Check that all the connections are correct and wire sizes are suitable.
2)
Ensure all parameters are configured correctly and oil pressure light is on.
3)
Ensure the controller DC power supply is fused and correctly connected to the positive and
negative of starter battery.
4)
Take proper measures to prevent the engine from starting (e. g. unplug fuel valve wire).
After checking that there are no faults, connect the starter battery, change start key position
from OFF to ON, and the controller will carry out the procedure.
5)
Then change start key position to START to start cranking. After the engine is fired, remove
start key; voltage, frequency and power windows will show true collected values.
6)
For further information please contact SmartGen services.
9.

TYPICAL WIRING DIAGRAM

Typical wiring diagram is shown below:
HGM501 Genset Controller User Manual
Fig.4 – HGM501 Typical Application Diagram
Page 15 of 17

Advertisement

Table of Contents
loading

Table of Contents