10 COMMISSIONING

1)
Start the genset, perform on-load test and then stop the genset respectively.
2)
Close the genset switch, parallel the genset to Bus and then open the genset switch respectively.
3)
Set each genset (e.g. HGM9510) as auto mode.
4)
Set the HGM9560 controller as manual mode, when the mains is normal, perform mains switch
close/open test and check if the mains switch is normal; then open the mains switch if it is ok.
5)
Start the HGM9560 controller manually, when the bus is normal, perform bus switch close/open test and
check if the bus switch is normal; then open the bus switch if it is ok.
6)
Press the mains close button, the bus will anti-synchronize to mains; then mains close after the
synchronization is successful and parallel running is beginning.
7)
Perform on-load test and load transfer test.
8)
Set the HGM9560 controller as manual mode, the controller will control the genset to start/stop and share
load automatically according to the preset condition.