GSM-204-423
Installing the
auxiliary
equipment
housing
template
The template (shown in Figure 5-2) must be secured to the concrete floor before
drilling the holes for the M12 anchor bolts.
1.
2.
3.
4.
5.
6.
7.
31st Oct 01
Procedures for installing the auxiliary equipment housing
If required, place the cable shroud template on the ground against the
appropriate side of the BTS cabinet, so it will act as a spacer between the
BTS cabinet and the auxiliary equipment housing.
Move the auxiliary equipment cabinet template to the selected mounting
position, flush against the cable shroud template.
Mark the positions of the two template mounting screw holes in the
template.
WARNING
Wear safety glasses and a dust mask when drilling holes.
CAUTION
Drilling concrete flooring produces cement dust, which is
harmful to equipment and wiring. Protect the cabinet and
any nearby equipment from dust. Use a tarpaulin, cloth, or
plastic sheeting to cover exposed equipment. Clean up
any accumulated debris from the anchor installation
carefully before uncovering the equipment. Use drilling
equipment suitable for cutting steel reinforced concrete.
Drill out the two holes to a depth and clearance for No. 10 screws.
Fit plastic expanding plugs into the mounting holes.
Position the template over the mounting holes and secure using No. 10
screws.
When satisfied that the template is correctly installed, carry out procedure
for installing the cabinet anchor bolts.
Installation & Configuration: Horizon macro outdoor