This procedure must be carried out after the first cabinet has been bolted in
position and before any additional cabinet or auxiliary equipment housing (AEH)
is bolted down. Use the shroud template as an aid to determine spacing.
To install the cable shroud between adjacent cabinets or between a cabinet and
the auxiliary equipment housing, proceed as follows:
1.
2.
3.
4.
5.
6.
7.
8.
9.
The procedure for installing the cable shroud between cabinets and/or the
auxiliary equipment housing is now complete.
31st Oct 01
NOTE
The procedure for installing the shroud between two BTS
cabinets or two auxiliary equipment housings is basically
the same and is described below.
Open the lids on both cabinets.
Remove the two cabinet end plates from the cabinet sides facing each
other and replace with expansion plates, (see Connecting antennas in
Chapter 3 of this category).
Attach the rear panel of the shroud to the first cabinet and then attach the
front panel, as described previously in Procedure for attaching the cable
shroud frame to the BTS cabinet.
Prior to manoeuvring a second BTS cabinet or AEH into final position:
Remove the expansion plate pass through blanks, as required.
Undo the two hose clips securing each RF cable gland housing and
remove gland assembly, (if RF connection required).
Feed any dc power cables through the expansion plates.
Adjust the position of the second cabinet or AEH, if necessary, so that its
side is flush against the sides of the shroud and the bolt holes identified in
Figure 4-2 and Figure 4-6 are aligned. Bolt the rear and front panels of the
shroud to the side of the housing through these holes.
Make the dc power, fibre optic and signal connections between the two
cabinets, (see Figure 4-8 for routeing), and then bolt the cabinet or AEH to
the floor.
Make any RF connections, appropriate to the site configuration (see
Figure 4-8 for routeing and Suggested RF configurations), between the
cabinets. Remove the required number of blanking plugs and fit both
multi-cable glands over the RF cables.
Fit rubber housing around left cable gland and insert into left side
expansion plate, as shown in Figure 4-7 secure with two hose clips.
Repeat for right side gland.
Slide the shroud top cover in place and secure to the rear panel and front
panel by tightening the four anti-tamper screws, as described previously in
Procedure for attaching the cable shroud frame to the BTS cabinet.
Installation & Configuration: Horizon macro outdoor
68P02902W03-A
CONTROLLED INTRODUCTION
Cable shroud installation procedures
Inst. 4–7

Advertisement

Table of Contents
loading

Table of Contents