ELECTRICAL
5. Repeat steps 3 and 4 to remove the opposite control
rod from the control bar/bail assembly.
6. Remove the bail from the T-Bar handle by sliding it
off the OPC Switch mounting bracket and remove it
from the machine (Fig. 1428).
7. Remove the OPC switch from the switch mounting
bracket (Fig. 1429).
9
9-16
Fig 1428
PICT-1785a
Fig 1429
PICT-1786
OPC Switch Installation (T-Bar)
1. Install the OPC switch into the switch mounting
bracket on the T-Bar (Fig. 1430).
Fig 1430
2. Position the bail onto the OPC handle by sliding
the switch bracket up around the switch mounting
bracket (Fig. 1431).
Fig 1431
Floating Deck Mid-Size Service Manual
PICT-1786
PICT-1785a